We programmed and commissioned two complete production lines for valve body for automatic transmissions for the American Chinese automobile manufacturer Changan-FORD.
Technical Details
Project
- Production line for valve body for automatic transmissions
Installation
- Raw part basket buffer with two loading stations to load the raw parts
- Gantry to load raw parts on the adapter in the logistic module
- Logistic module for storing the adapter, 2 Atlas Copco bolt station for bolting and unbolting the parts on the adapter
- Gantry to load and unload the adapter plates in the Heller tooling machines and into the washer
- Gantry to load the finished parts from the adapter into the intermediate basket buffer
- Gantry to unload the intermediate basket buffer, load the parts into the high-pressure washer, unload the high-pressure washer and load the parts onto the finish part conveyor
Controls
- 10x SINUMERIK 840D sl for gantries, basket buffers and logistic modules
- 2x SIMATIC S7-300 for the finish part conveyors
- 1x SIMATIC S7-400 for the GPTS system
Features
- Global part tracking system (GPTS)
- Atlas Copco bolt station
- Cognex cameras to read DMC
- Cycle time 54 seconds